I have been in Houston last few days visiting my family after Hurricane Ike.
Lots of tree damage, like tress splitting houses neatly into 2 halves. A
VERY large metal billboard sign + post impaled into an apartment complex. No
one had electricity for 12 days, it was a zoo.
Last week I mainly shipped MOTM 2.0 orders that had been piling up. BTW:
nearly out of all CEM ICs, guess that is the end of that :(
Will be able to ship many kits this week, the rest of October I will not
have nearly as much available time as I have had in Sept. I want to start
shipping MOTM-730s in late Oct/early Nov. if I can get the CPU boards
stuffed. I have a lot going on right now, I'll do what I can. My tech Shane
is finishing up 12 MOTM-440 pc boards, and then he starts on 12 MOTM-300
boards which is 1/2 of the VCO assembled backlog.
I also owe Analog Haven more Frac modules, they will ship Oct 6th.
Paul S.