a) By Friday, the Rev B MOTM-730 pc board should arrive, and towards the end
of the month I will have the pre-production painted/screened sheet metal
(just a couple of panels) to verify everything will stack up properly. I
don't anticipate any issues, but you never know. If everything is OK, by the
4th of July holiday (see below) I will "sign off" on the design and order
production front panels and all the parts (I have the PICs and the
displays/bezels already).

b) I am taking a MOTM break July 4 to July 12. Hey, Europe takes off most of
August :)

c) I am almost 100% done with all existing MOTM 2.0 orders, I have like 4
left and 3 of those are quite large. If you have an order less than #975
that is a MOTM 2.0 order (not kits or modules, just parts) please email me
and let me know (if your initials are KH I will email you about yours).

d) I will start shipping out the first batch of MOTM kits ~ July 17th. I
won't be able to ship all of them until the end of August. I got all the pc
boards in I ordered, I still have a lot of sheet metal due in and a few
panels to order ('700s mostly). I will ping the vendor tomorrow for due
dates. I still have a lot to do and this is still a hobby (nights &
weekends) but things are looking better. I will have 9 consecutive days
coming up when we are shut down for inventory/audits for the day job, I will
be able to do MOTM most of that time. Some of that will be to get the
prototype CGX pc boards & sheet metal on order. I also have not been able to
get going on the '650 reordering, I need to do that AND get Analog Haven 40
more Frac modules.

At least I'm not bored.