Where does the backlog of MOTM-650 orders fit into the shipping schedule?
Richard Brewster
http://www.pugix.comPaul Schreiber wrote:
> OK, I have the current kits (already bagged up, sitting on the shelf), panels,
> pc boards and "loose parts" all counted up.
>
> a) I have send the first shipment list to Indiana. The people on this list are
> the ones that offered to pre-charge, and a few that ordered before the actual
> start of the sale.
>
> b) I tried to pick the people that would get "ship complete" right away. What I
> don't want to happen is split 1 order into 3 shipments as parts arrive (OK the 1
> exception is a certain person that ordered 28 kits at once).
>
> c) this first batch should ship out, no later than Aug 1st. As ∗always∗ (cough):
> I will send an email when it ships.
>
> d) This first batch is about 24 total kits. Once these are shipped, then next
> set of kits will ship. This set will depend on what we have in stock as of
> August 1st (NOT what has been ordered). I am ∗guessing∗ this will be another 25
> or so kits (out of the 400+ ordered). I expect all of these to ship no later
> than Aug. 15th.
>
> e) the item that will hold up shipments will be either wire or front panels
> (both of these 2 suppliers are slow). So, if you do not get a "happy email" by
> August 15th, then that means you (and about 56 other people) will have to ∗wait∗
> for the parts to arrive. Now, I am ∗ordering∗ these on Monday the 24th. I
> ∗expect∗ then to arrive around Sept 1st. That means if you are order #120 or
> later, ∗chances are∗ you will not see any modules until after Sept. 1st.
>
> f) Once all these parts arrive, it will THEN take at ∗least∗ 4 weeks to ship the
> remaining kits. So, if you are past Order #200, ∗chances are∗ you will not see a
> kit until October.
>
> Hopefully, all of the above is a "worse-case scenario" and the ship times will
> be sooner. But, past history has shown the panel vendor is running 5-7 weeks on
> average.
>
> Paul S.
>
>
>
>